Northstar Update
Slab is poured!! As many may not know, there is alot of work that occurs before the slab is poured. You have to compact the subgrade to 98% proctor compaction but that was after we poured 41 additional piles with steel plates within the building for placement of heavy machinery.
Then you need to install your radon pipe and pit to mitigate any radon release. Once that is done, then the final layer of gravel is laid before all the rebar is installed. After rebar installation, the area is ready for concrete and the slab is poured! Then the finishers get on the slab to treat the surface while it is curing. Great job by Engelhart Construction Ltd. and Dynamic Concrete Pumping Inc.! Concrete precast sandwich panels are en route!